Joe Rockhead’s will close for one week in October to replace flooring and perform general maintenance. Rock Oasis and Up The Bloc will be unaffected.
Closure Schedule
Saturday October 5: OPEN 9am - 1pm (EARLY CLOSURE)
Sunday October 6 to Sunday October 13: CLOSED
Monday October 14: OPEN 9am - 9pm (Thanksgiving Monday)
Tuesday October 15: OPEN 7am - 11pm (Regular hours resume)
Membership Adjustments
Prepaid Rockhead’s members will have their termination date extended by 8 days. Monthly Subscription (“EFT”) members will have their October bill prorated to reflect a 8 day closure. This bill will be charged on October 1.
Members are permitted to climb at Rock Oasis and Up The Bloc during the closure. Single-gym members (Welcome Pack and Semester Pass) are also allowed to climb at these gyms during the closure period.
To freeze or terminate your membership, use the Membership Change Form.
Updates from the gym
Day 1
Members Gerry, Sujoy, Jessica, Kyle, Luis, and Adam helped us rip up the gray carpeted mats.
Day 2
Former Rockhead’s instructor Sam replaced the bulk of our overhead lighting.
Day 3
The Circuit Wall mats were torn up and removed, and lobby walls got a fresh paint job.
Day 4
A team from Flashed started installing the new Circuit Wall floor while Deb and Luigi replaced quick draws in the Lead Cave.
Day 5
The Circuit Wall foam was completed and left to dry. The old gray carpets were relaid as a new base layer before the installation of more foam and a new top layer of carpet.
Day 6
Circuit Wall mats were wrapped and tightened, and the multilayer gray floors were finished in the Lead Cave.